Last updated: November 2026

When you signed your contract, your contractor should have handed you a one-page Notice of Procedure. It warns that Oregon law sets steps you must take before you can arbitrate or sue over construction defects. Those steps are in ORS 701.560 to 701.595. Miss them and your case is dismissed.

When the rule applies

The procedure covers a claim by an owner against a contractor, subcontractor or supplier arising out of a defect in the construction, alteration or repair of a residence, including any system, component or material built into it (ORS 701.565(1)). "Residence" means a residential structure as defined in ORS 701.005, plus common property and condo common elements (ORS 701.560).

It does not apply to (ORS 701.600):

  • Personal injury or death claims
  • Complaints filed with the CCB under ORS 701.139
  • Complaints filed in small claims
  • Claims against architects registered under ORS 671.010 to 671.220
  • Your counterclaim when the contractor sues or demands arbitration first

So you can file a CCB complaint, or a small claims case, without this notice. You need it before circuit court or arbitration.

Step 1: Send the notice of defect

Send it by registered or certified mail, return receipt requested. For a contractor or subcontractor, use the last known address in CCB records. For a supplier, use its Oregon business address, or its registered agent if it has none (ORS 701.565(2)).

The notice must include (ORS 701.565(3)):

  • Your name and mailing address, or your lawyer's
  • A statement that you may seek to compel arbitration or bring a court action
  • The address and location of the home
  • A description of each defect, the remediation you believe is necessary, and any incidental damage repair won't cure
  • Any report or document showing the defects and damage

Within 14 days of receiving it, the contractor must forward a secondary notice to any other contractor, sub or supplier it believes may be responsible (ORS 701.570(1)).

Step 2: Let them look

A party that received the notice may ask, in writing, to visually examine the home within 14 days of receiving it, and then ask to inspect within 14 days of that examination (ORS 701.570(2)โ€“(3)). You must make the home available for the visual examination during normal business hours, or as agreed, within 20 days of the request, and for the inspection at normal business hours or a mutually agreeable time (ORS 701.575).

An inspection can include reasonable testing. Unless you agree otherwise, the inspecting party must repair damage it causes, and unrepaired inspection damage can be claimed later (ORS 701.575(3)).

Step 3: The written response

Unless you agree to a different time, each party that got a notice must send you a written response within 90 days of receiving it, by registered or certified mail (ORS 701.570(5)). For each defect, the response must acknowledge it, describe a different defect, or deny it. It must include any inspection report, and either offer to repair (with a completion date), offer a stated amount of money (with a payment date), or deny responsibility.

Step 4: Accept, reject, or proceed

You have 30 days after receiving an offer to accept it in writing. If you don't, it is treated as rejected (ORS 701.580(1)). If you accept and the repair or payment is completed, that settles your claims for the defects in the offer, and only those.

You may compel arbitration or sue if the contractor doesn't respond on time, offers neither repair nor money, makes an offer you reject as insufficient, or fails to perform an accepted offer (ORS 701.580(4)). The notice and inspection report are admissible in that case (ORS 701.580(5)).

Your filing deadline is extended

Sending a notice of defect within your time to sue extends that time, despite any statute of limitation or repose, until the latest of (ORS 701.585):

  • 120 days after you receive a response that offers neither repair nor money
  • 120 days after you reject an offer
  • 30 days after the completion date in an offer you accepted

The extension doesn't shorten any limitation period you already have.

If you skip the procedure

If you arbitrate or sue without following ORS 701.565 and 701.575, the arbitrator or court must dismiss without prejudice. You can't start a new case until you follow the procedure (ORS 701.595). The CCB's form adds that "there are strict procedures and deadlines" and suggests talking to an attorney (Notice of Procedure).

Related pages

Sources

Frequently Asked Questions

Do I have to notify my contractor before suing in Oregon?

For a claim about a defect in a residence, yes. ORS 701.565 bars an owner from compelling arbitration or starting a court action against a contractor, subcontractor or supplier unless the owner first sent a notice of defect and made the home available for inspection. A case filed without it is dismissed without prejudice (ORS 701.595).

How long does the contractor have to respond to a notice of defect?

Unless you agree otherwise, 90 days after receiving the notice (ORS 701.570(5)). The response must acknowledge, describe or deny each defect and may offer repairs or money.

Does the notice of defect apply to small claims court?

No. ORS 701.600 excludes complaints filed in small claims, CCB complaints, personal injury and death claims, and counterclaims against a contractor's own claim.